Design Process Overview

  1. AASHTO Soil Classification.

  2. Analytical Baseline Analysis.

  3. Estimate Starting Soil Mix Design.

  4. Strength Testing and Structural Design.

  5. Treatability Analysis.

  6. Final Mix Design Verification

  7. Product Structural Design.

Construction Process Overview

  1. Materials excavated and stockpiled.

  2. Screen and separate oversize material from soil.

  3. Re-test soil to ensure material consistency with the sample.

  4. Prepare and manage on-site quality control and safety plans.

  5. Set up on-site pug mill(s) and produce proprietary Emulsified Treated Base ("ETB") at a production rate up to 300 tons per hour per pug mill.

  6. Place and compact the ETB in accordance with acceptable construction practices and the project’s structural specifications.

 